Rehabilitation of Al-Anaz Bridge in Al Anbar Governorate
Scope of Work :
Al-Anaz Bridge was bombed and destroyed by terrorist acts, which resulted in the destruction of five sections of the bridge with a total length of 150 m. This project is deemed to be one of the projects of the Emergency Development Operations Project in Iraq submitted by the Ministry of Construction and Housing. The work method includes preparations, demolition and removal of rubble for five sections, processing of damaged concrete parts, concrete works, manufacture of iron joists for the bridge and complementary works.
Project Location : Al Anbar City
Contract Value (US$) : 2,598,250
Contract Duration : 350 days
Contract Start Date : 20/ Oct / 2018
Contract Completion : 20/ Oct / 2019