Reconstruction of highway bridges and arches No. 1
Scope of Work :
The project includes the reconstruction of two bridges on the highway located in Al Anbar Governorate, the western sector, and the arches between the two stations (S090-S29.8, S52.1-S). in addition, the project is considered one of the projects of the reconstruction fund for the affected areas signed with the Ministry of Construction and Housing, as the emergency loan for projects funded by the World Bank. The project includes the reconstruction of a bridge over the track east of Fallujah and a bridge near the Samarra junction on one of the valleys. The work includes the construction of four tube arches and five box arches of different diameters. The work was completed according to the quality requirements and the instructions of the World Bank projects in terms of ensuring occupational safety. The work plan included preparations, drilling and burial works, erection of arches, tiling works, concrete works, foundation works for bridges, concrete works over foundations (pillars and pouring pillars), fabrication of pre-stressed concrete joists, erection and installation of joists as well as complementary works and inspections.
Project Location : Al Anbar City
Contract Value (US$) : 3,000,000
Contract Duration : 510 days
Contract Start Date : 15/ Nov / 2019
Contract Completion : 15/ Apr / 2021