Repair of al-Anaz Bridge in al-Anbar Governorate
Scope of Work :
The scope of work includes the demolition of affected spaces (5 spaces with a length of 150 m), and the main stent followed by destruction of the columns to the very top until reaching up to the stronger pieces of concrete.

Once the above is accomplished, it is followed by the rehabilitation work, with the casting and cutting of columns from the top, as well as the main support. This is followed by the manufacturing of Iron tributaries totaling 15, the maintenance of tributaries (5) and their rubber supporting parts (40), as well as the rehabilitation of damaged spaces of the bridge by adding a layer of asphalt. The work also includes the preparation and instillation of the expansion joints, the lighting poles, with all the accessories and with the metal protection fence, and sanitation and drainage works. This construction is set to connect the Amiriyeh Fallujah Bridge to the Anaz area, thus making it one of the most important bridges from a Geographical perspective. The bridge lay on Euphrates river connect to bank Al Waffaaa Discrete in Al Anbar Gov. and Al Zeidan Discrete in Baghdad Capital
Project Location : East of Fallujah city Al Zidan District Al Anbar Gov.
Client : Ministry of Construction and Housing Roads / Roads &Bridges Directorate, Final by World Bank
Contract Value ( US$ ) : 2,598,250
Contract Duration : 365 days
Contract Start Date : 22 / Apr / 2018
Contract Completion : 22 / Apr / 2019